Dua Villas @ ONE residence, Penang
 

 

Overall view (left)

 

T11 Lot 52 -63 casted until stump

 

T12 Lot42-51 gbeam casted.Backfilled &levelling work in progress

 

T10 Lot81-76 gbeam casted.Lot 75-70 constructing gbeam fwk in progress

 

 

 

view from entrance

 

view from crusher run stockpile(centre)

 

view from crusher run stockpile(left)

 

view from crusher run stockpile(right)

 

 

View From Mutiara Perdana

 

Overall View 2

 

Overall View 3

 

Overall View 4

 

 

Semi-D Roof beam completed

 

Brickwork in progress

 

1st fl. beam & slab fwk in progress

 

Roof beam fwk in progress

 

 

Roof structural work in progress

 

Grd fl. brickwork in progress

 

External painting & tiling work in progress

 

Overall view

 

 

Roof covering completed

 

Roof beam in progress

 

Plastering will be commenced

 

Brickwork in progress

 

 

Plot9-16 Finishing Work of Second Block Terrace House Is expected to Complete in March 2011

 

All Semi D Structural Work Is expected to Complete By Mid March2011

 

Plot 106-118 Last Block of Terrace House Structural Works Completed

 

All Semi D Structural Work Is expected to Complete By Mid March2011

 

 

Clubhouse - Foundation works commenced

 

Semi-D - Structural work of last pair Pt 119 and 120 completed


Terrace - Plot 82-87 - External plastering in progress

 

Infrastructure - Works commenced

 

Overall view (right)

Overall view (left)

 

Overall view of club house & swimming pool

 

T5 (124-135) construction of gate pillars & post box in progress

 

 

S4 (7 & 8) Semi-D Tiling work in progress

 

T4 (26-33)rear. Piling work in progress for perimeter fence wall

Overall view (left)

Overall view (right)

 

 

Pt 26-51 - Perimeter fencing in progress

 

Pt 82-93 - Fencing and gate pillar in progress

 

Overall view (left)

 

Overall view (right)

 

 

Pt 52-63 - Painting work in progress

 

Open Space behing Pt 52-63 and 70 -81

 

Club house - Work in progress

 

TNB substation at club house completed

 

 

Swimming and club house- work in progress

 

S4 plot 64-69 - external painting in progress

 

Perimeter Fencing - Work in progress

 

Bungalow - External plastering in progress

 

 

TNB substation - Completed

 

Club house & swimming pool- Works in progress

 

Semi-D -Fencewall in progress

 

Semi-D - Finishing works almost completed

 

 

Semi-D - Plot 64-69 building completed

 

Part of Perimeter fencing completed

 

 

Plot 124-135 - Building works completed

 

Swimming pool

 

 

 

Entrance Arch and Guard house - Works started

 

Clubhouse - Finishing work in progress

 

Roadworks - 60% completed

 

Fencewall Feature

 

 

TNB - Underground cabling in progress

 

Open space behind Pt 106-135

 

Guard house & rubbish chamber - Work in progress

 

Overall view right

 

 

Bungalow - Completed 121

 

Semi-D - Completed

 

Overall view of swimming pool and club house

 

Terrace - Completed

 

 

Clubhouse - Work in progress

 

Facility - Sub station completed

 

Clubhouse - BBQ pit

 

Facility - Work in final stage

 

 

Completed Clubhouse

 

Completed Open Space

 

Completed Lintang Rajawali 3

 

Completed Lintang Rajawali 4

 

 

Semi-D - Feature at Side Elevation

 

Terrace House - Night Scene

 

Swimming Pool - Night Scene 1

 

Swimming Pool - Night Scene 2

 
 
 
  Back to top